 01  Blue Stakes

Prior to the start of construction, Blue Stakes will come to the area to mark existing utility lines.  
*NOTE:  This process is managed by a separate organization.

 02  Construction Begins Underground Work

As fiber construction begins, large equipment may be seen parked around the neighborhood. Potholes may also be seen on or around property areas as conduit lines are installed underground. 

*NOTE: Click on each image to expand.

 03  Vault Installation

Another set of digging occurs as vaults are installed. These vaults are placed strategically on the easement of properties.

 

Prior to digging, homeowners will receive a notification via door hanger regarding vault placement.   

 04  Fiber Splicing

Once the vault is installed, a fiber splicing technician will create routes for fiber internet to be made accessible to residents.