CLINTON CITY FIBER
Clinton City Residents - SEPT 13, 2023: Connext Clinton City Fiber Project Update
ALL OF CLINTON CITY IS NOW LIVE!
CONNEXT HAS COMPLETED THE FIBER INFRASTRUCTURE FOR THE ENTIRE CLINTON CITY FIBER PROJECT!
Phases 1 - 5 are NOW LIVE
Please see the interactive map below for a look at our progress. If you are in one of the Phases listed below call to get CONNECTED NOW. All homes in Phases 1 through 5 currently remain eligible for our FREE Fiber Connection and Installation Promotion.
Phase 1 - Neighborhood Groups 1 - 12: NOW LIVE!
Infrastructure Complete and the Fiber is LIVE in all Groups.
6000 S to 1800 N (from North to South)
The city boundary line at the train tracks to 1500 W (from East to West)
Phase 2 - Neighborhood Groups 13-22: NOW LIVE!
Infrastructure is Complete and the Fiber is LIVE in all Groups
2300 N to 1800 N (from North to South)
1500 W to 3000 W (from East to West)
Phase 3 - Neighborhood Groups 23 - 33: NOW LIVE!
Infrastructure is Complete. The Fiber is Live in all Groups.
6000 S to 2300 N (from North to South)
2000 W to the Far western edge off Clinton near Crane Field (from East to West)
Phase 4 - Neighborhood Groups 34 - 50 NOW LIVE:
Infrastructure Installation is Complete and is NOW LIVE! Our fiber specialists have completed pulling fiber and splice the fiber in groups 45-50.
Phase 4 / 5 - Neighborhood Groups 51-69: NOW LIVE!
Infrastructure Installation has ben completed, FIBER IS PULLED AND SPLICED! This is the last phase of the Clinton City Fiber Project. Please Click Here to see the next steps in the construction process and to how your property may be affected by installation process.
Residents in the areas shaded in
BLUE, GREEN, and ORANGE on the map.
PLEASE CALL (801) 686.2468 or email
Marketing@Connextllc.com to confirm you would like fiber run to your home and to take advantage of our current promotion, a Fiber Connection and Home Installation at no charge to you.
Let Us Know if You're Interested!
If you're ready for fiber in your neighborhood next please submit your info on the form to the left.
Our construction crews break ground and build the areas with the highest level of interest.
Submitting the form and encouraging your neighbors to do the same will help us plan our build.
MAP KEY
Fiber Available!
Construction Complete
Construction In Progress
Pending Fiber Construction
Planned Construction
THE COUNTDOWN TO COMPLETION..

2.11.2022: The Connext Team, Mayor Brandon Stanger and City Officials Celebrated the First Clinton City Project Connections with Balloons, Ribbon and BIG SCISSORS